Puerto Rico Is Still Waiting

Nine years after Hurricane Maria, FEMA has committed $30.0 billion to rebuild Puerto Rico — and as of November 4, 2026, only $7.45 billion of it, 24.8 percent, has been paid. Where the rebuilding money stalls, and why Puerto Rico's unfinished recovery is a stress test for the whole American disaster system.

By Herbert V. TrembleNovember 16, 20266 min read
Hillside homes with blue tarp roofs in Naguabo, Puerto Rico, after Hurricane Maria

Nine years after Hurricane Maria, the money to rebuild Puerto Rico has largely been promised. Much of it has still not been spent.

By Herbert V. Tremble, Founding Principal, R3SULTS. An article in the R3SULTS Disaster Relief and Recovery Series. Published November 16, 2026.

Two numbers tell the story

Every disaster recovery eventually comes down to two numbers: how much was committed, and how much has actually been paid. In Puerto Rico, nine years after Hurricane Maria, those two numbers are far enough apart to be the whole story.

For the rebuilding itself — the permanent work:

  • schools
  • roads
  • water systems
  • public buildings
  • the power grid

— FEMA has committed $30.0 billion. As of November 4, 2026, Puerto Rico's Central Office for Recovery, Reconstruction and Resiliency (COR3), which manages the federal money and pays it out, had paid $7.45 billion of it. That is 24.8 percent.

Three quarters of the rebuilding money, nine years after the storm, has not reached the work.

I have worked disaster recovery since Hurricane Andrew in 1992, and I have seen slow recoveries. Slow is normal. A decade is not.

The emergency money moved. The rebuilding money did not.

The contrast inside Puerto Rico's own numbers shows this is not simply a story of an island that cannot spend. Of the $6.03 billion FEMA committed for debris removal and emergency protective work, 99 percent has been paid, most of it in 2018 and 2019. When the work was urgent and the rules were built for speed, the system moved money at speed.

Permanent work runs on a different machine. FEMA's Public Assistance program is, at its core, a reimbursement program: the town, agency, or utility does the work, documents every cost, and gets paid afterward. After Maria, most large projects were converted to fixed-cost estimates — a set price agreed up front — which was supposed to simplify things.

In practice it front-loaded years of estimating, review, and negotiation before construction could begin, and it left local governments, most of them small and many of them broke, to finance multimillion-dollar projects out of pocket while they waited to be made whole.

The results are in COR3's records. None of the 207 sites in the Department of Education's fixed-cost program is finished.

Of $257 million committed for transmission lines under the power utility's program, 0.6 percent has been paid. COR3 itself cites a harsher yardstick — money paid on completed projects — which it put at about 8 percent in September.

Where it stalls

Some of the stall is paperwork with real consequences. Every large project passes environmental and historic preservation review.

The Government Accountability Office reported in July that all 14 FEMA staff conducting those reviews for Puerto Rico grid projects were temporary employees, and that turnover among them rose from 3 percent in 2021 to 19 percent in 2024. Every departure restarts relationships, reopens files, and adds months.

Washington did try one real fix. Since June 2022, Working Capital Advances have let agencies and towns draw money before the work is done instead of after. The advances account for $4.92 billion of the $7.45 billion paid — most of it.

But an advance is not a finished project. COR3's interim executive director told El Nuevo Día in September that the office had recovered advances in 2025 and 2026 from recipients that were not ready to start. And payments for permanent work fell by 29.5 percent in 2025, a drop COR3's June report to Congress records without explaining.

The grid is the proof

Nowhere is the gap more visible than in the power system Maria destroyed. FEMA, HUD, and the Department of Energy have obligated about $14.3 billion for grid recovery and modernization, according to the GAO's July 1, 2026 report. About 75 percent of it has not been disbursed.

As of December 2025, nine of 258 large FEMA-funded grid projects were complete.

Puerto Rico has lived the difference: an island-wide blackout in 2025 lasted two days, and rolling outages continue. A RAND study projected that at the 2023 pace of spending, the recovery "will not be finished until 2051."

A dam, and what August signaled

The money has not stopped moving entirely. On August 10, 2026, FEMA obligated more than $513 million for nine recovery projects, eight of them tied to Maria — including $509 million for permanent repairs to the Guajataca Dam, the structure whose damaged spillway forced evacuations in the weeks after the storm.

It is a significant obligation, for a real and dangerous problem. It is also, nine years on, an obligation: the beginning of the same long pipeline this article describes, not the end of it.

What this means for the next storm

Puerto Rico's unfinished recovery is usually discussed as a Puerto Rico problem. It is better understood as a stress test the whole American disaster system is failing in public. The same reimbursement model, the same fixed-cost machinery, and the same review bottlenecks now govern recovery from Florida to the territories — Puerto Rico simply got the largest dose, earliest, with the least margin for error.

The next major hurricane to hit the island will not land on a recovered Puerto Rico; it will land on top of this one, on a grid still being rebuilt and schools still waiting, and every unspent dollar from 2017 will compound into the damage figures of that storm. The lesson is not that the money was never sent. It is that in disaster recovery, an obligation is a promise — and a promise kept nine years late is a different thing from help.

Where to find help

If you or your community need help with disaster relief, recovery, or preparedness, you can find solutions at R3sults.com and R3sults.org. In Puerto Rico, recovery from Maria and later disasters is still active: check your status or apply for federal assistance at DisasterAssistance.gov or through FEMA at 1-800-621-3362, and follow project-level recovery funding through COR3 and the Puerto Rico disaster recovery transparency portal at recovery.pr.gov. Reach him at hv.tremble@r3sults.com or by phone: Business +1 954-231-1750, Mobile +1 347-874-6296.

Available for consultations, operational support, crisis problem-solving, public speaking, and podcast appearances. Serving all tiers of government, commercial enterprises, and residential communities in disaster relief management and preparedness. From local community planning to large-scale federal response: no job is too big or too small.

Sources

Central Office for Recovery, Reconstruction and Resiliency (COR3), payment records as of November 4, 2026 (permanent work: $30.0 billion committed by FEMA, $7.45 billion / 24.8 percent paid; debris removal and emergency protective work: $6.03 billion committed, 99 percent paid; 207 Department of Education fixed-cost sites, none finished; transmission lines $257 million committed, 0.6 percent paid; $4.92 billion of payments made as Working Capital Advances), per COR3's transparency portal ledger. COR3, Fifteenth Progress Report on the Economic and Disaster Recovery Plan to Congress, June 30, 2026 (permanent-work payments down 29.5 percent in 2025). U.S. Government Accountability Office, "Puerto Rico Grid Recovery: Limited Progress Toward Stability and Opportunities Exist to Improve Federal Assistance," GAO-26-107772, released July 1, 2026 (about $14.3 billion obligated by FEMA, HUD, and DOE for grid recovery; about 75 percent undisbursed; 9 of 258 large FEMA-funded projects complete as of December 2025; all 14 FEMA environmental and historic preservation reviewers for grid projects temporary staff, turnover 3 percent in 2021 to 19 percent in 2024). Puerto Rico Federal Affairs Administration, Governor's announcement, August 10, 2026 (FEMA obligations of more than $513 million for nine projects, including more than $509 million for permanent repairs to the Guajataca Dam). El Nuevo Día, September 2026 (COR3 interim executive director María L. Marín Colón on recovered Working Capital Advances and the roughly 8 percent paid-on-completed-projects figure), as reported October 16, 2026.